Financial Number:
433897-1-52-01
Project Length: 0.6 miles
Project Limits: I-95 / I-595 Interchange
Start Date: October 7, 2013
Completion Date: April 2, 2014
Contractor: Weekley Asphalt
Estimated Construction Cost: $5.9 Million
Scope of Work: Project improvements included adding bold landscaping, constructing tiered landscaping planters at seven locations, constructing two detention ponds, and installing an irrigation system.