Financial Number:
422796-1-52-01/ 422796-2-52-01
Project Length: 13 miles
Project Limits: I-95 from the Golden Glades in Miami-Dade County to Broward Boulevard in Broward County
Start Date: November 2011
Completion Date: February 2, 2017
Contractor: Hubbard Construction
Estimated Construction Cost: $120 Million
Scope of Work
This project, also known as, 95 Express Phase 2 will extend the existing express lanes north from the Golden Glades Interchange in Miami-Dade County to Broward Boulevard in Broward County. High Occupancy Vehicle (HOV) lanes are being converted to two express lanes in each direction. Other work includes: installing Intelligent Transportation System (ITS) and tolling equipment; bridge widening at specific locations; and installing noise barrier walls between Hollywood Boulevard and Taft Street.
Click here for upcoming I-95 lane closures |