Financial Number:
428732-1-52-01
Project Length: 1.82 miles
Project Limits: Oakland Park Boulevard from east of I-95 to NW 31st Avenue
Start Date: January 25, 2016
Completion Date: January 6, 2017
Contractor: Community Asphalt Corp.
Estimated Construction Cost: $3.2 million
Scope of Work: The improvements include adding new traffic signals, pedestrian crosswalks, and pedestrian signal countdown timers at NW 23rd Terrace, installing irrigation sleeves for future landscape project in median along Oakland Park Boulevard, adding drainage inlets along Oakland Park Boulevard and installing traffic signals mast arms at NW 18th Avenue. Other improvements consist of removing old asphalt and resurfacing Oakland Park Boulevard within project limits, improving sidewalks and curb ramps to meet current ADA standards and adding or replacing signs and pavement markings.
Oakland Park Boulevard Roadway Improvements Project from east of I-95 to NW 31st Avenue