Oakland Park Boulevard Roadway Improvements Project from east of I-95 to NW 31st Avenue

Financial Number: 428732-1-52-01

Project Length: 1.82 miles

Project Limits: Oakland Park Boulevard from east of I-95 to NW 31st Avenue

Start Date: January 25, 2016

Completion Date: January 6, 2017

Contractor: Community Asphalt Corp.

Estimated Construction Cost: $3.2 million

Scope of Work: The improvements include adding new traffic signals, pedestrian crosswalks, and pedestrian signal countdown timers at NW 23rd Terrace, installing irrigation sleeves for future landscape project in median along Oakland Park Boulevard, adding drainage inlets along Oakland Park Boulevard and installing traffic signals mast arms at NW 18th Avenue. Other improvements consist of removing old asphalt and resurfacing Oakland Park Boulevard within project limits, improving sidewalks and curb ramps to meet current ADA standards and adding or replacing signs and pavement markings.

PDF IconOakland Park Boulevard Roadway Improvements Project from east of I-95 to NW 31st Avenue

Click here for upcoming lane closures

 

Project Photos

Pre-Construction

Click to view enlarged version/details
Pre-construction Photo

During Construction

Click to view enlarged version/details
Pre-construction Photo Pre-construction Photo Pre-construction Photo Pre-construction Photo
Pre-construction Photo Pre-construction Photo
 

Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express