Riverland Road north of I-595 in Fort Lauderdale

Financial Number: 426853-1-52-01

Project Length: 0.17 miles

Project Limits: Riverland Road at SR7/US441

Start Date: February 2012

Completion Date: May 25, 2012     

Contractor: Horizon Contractors Inc.

Estimated Construction Cost: $228,612.11

Scope of Work
Safety improvements being made at this intersection included extending left turn lanes, pedestrian signal upgrades, installing video detection equipment on existing traffic signals and sidewalk repairs.

Click here for upcoming Riverland Road lane closures

 

Project Photos

Pre- Construction

Pre-Construction Photo 01 Pre-Construction Photo 01
Click to view an enlarged version Click to view an enlarged version

Project team will install a Broward County bus pad

Project team will install curb ramps at this corner

During Construction

During Construction Photo
Click to view an enlarged version  

Completed sidewalk at the SW corner of SR-7 and SW 21st St.

 

 