Financial Number:
429739-1-52-01
Project Length: 0.380 miles
Project Limits: Sheridan Street from the Intracoastal Waterway Bridge to A1A in Hollywood
Start Date: August 18, 2014
Completion Date: March 31, 2015
Contractor: Kiewit Infrastructure
Estimated Construction Cost: $2.1 million
Scope of Work
The improvements under this contract included removing old asphalt and repaving within the project limits, upgrading pedestrian features including curbs and ramps to meet ADA standards, improving drainage which will correct the standing water on the east end crosswalk , improving signalization by modifying the existing left turn green arrow from “protective and permissive” to only “protected”, installing new signing and street markings, adding a left turn only lane from northbound A1A onto Sheridan Street, adding two right turn lanes from eastbound Sheridan Street onto southbound A1A.
Click here for upcoming lane closures |