FDOT District Four - Broward County Header Image

State Road 870/Commercial Boulevard from University Drive to west of NW 64th Avenue

Financial Number: 424666-1-52-01

Project Length: 0.79 miles

Project Limits: State Road 870/Commercial Boulevard from University Drive to west of NW 64th Avenue

Start Date: March 2012

Completion Date: August 3, 2012

Contractor: Weekly Asphalt Paving Inc.

Estimated Construction Cost: $1 Million

Scope of Work
This project includes the following roadway improvements: drainage installation, removing old asphalt and repaving A1A through project limits, roadway widening, new sidewalks, new landscaping, curb and gutter and adding ADA ramps at intersections.

Click here for upcoming S.R. 870 lane closures

 

Project Photos

Pre-Construction

Pre-Construction Photo Pre-Construction Photo
Click to view an enlarged version Click to view an enlarged version

Eastbound lanes of West Commercial Boulevard before construction

Westbound lanes of West Commercial Boulevard before construction

During Construction

During Construction Photo During Construction Photo
Click to view an enlarged version Click to view an enlarged version

Materials are laid within project limits for safety during construction

Project team removing sidewalk along Commercial Boulevard

During Construction Photo During Construction Photo
Click to view an enlarged version Click to view an enlarged version

May 2012 - Newly paved eastbound lanes

May 2012 - Project team installs new signalization

During Construction Photo During Construction Photo
Click to view an enlarged version Click to view an enlarged version

July 2012 - Commercial Boulevard receives new paving and striped bicycle lane

July 2012 - Team installs new mast arm on the southside of Commercial Boulevard

 

 

Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express
zero