Financial Number: 435781-2-52-01
Project Limits: From NW 29th Street to north of SR 816/Oakland Park Boulevard
Start Date: July 2019
Completion Date: Early 2020
Contractor: H & R Paving, Inc.
Estimated Construction Cost: $1.4 Million
Scope of Work: Safety enhancements will address pedestrian mobility by constructing a 10-foot shared-use path along the east side of SR 7/US 441 within the project limits. A pedestrian safety barrier will be installed along the existing median to discourage mid-block pedestrian crossings. Improvements will also include a new northbound overhead sign, miscellaneous signage, paving, restriping, landscaping, and curb ramps to meet Americans with Disabilities Act (ADA) standards.
SR 7/US 441 Pedestrian Safety Enhancement Project
|