FDOT District Four - Palm Beach Header Image

State Road 80/Southern Boulevard Widening

Financial Number: 419345-2-52-01

Project Length: 7.2-miles

Project Limits: State Road 80/Southern Boulevard, from west of Lion Country Safari Road to Forest Hill Boulevard/Crestwood Boulevard

Start Date: July 2018

Completion Date: Early 2022.

Contractor: Community Asphalt Corp.

Estimated Construction Cost: $33 million

Scope of Work:
Work includes widening the existing roadway from four to six lanes, adding a 12-foot shared-use pathway on the north side of the roadway, adding bike lanes, milling and resurfacing, drainage improvements, adding lighting and signalization, installing curb and gutter, guardrails, minor median modifications and signage and pavement markings.

Click here for upcoming lane closures

 

 

Project Photos

Pre-Construction

Click to view enlarged version/details

During Construction

Click to view enlarged version/details

 

Please click on a link below to view construction projects
in other areas of Palm Beach County:
  I-95 Palm Beach CountyI-95 Construction Palm Beach County Northern Palm Beach CountyNorthern Palm Beach County
  Southern Palm Beach CountySouthern Palm Beach County Western Palm Beach CountyWestern Palm Beach County
  Central Palm Beach CountyCentral Palm Beach County Bridges Palm Beach CountyBridge Construction Palm Beach County
Florida Department of Transportation
Florida Department of Transportation
FDOT District Four Youtube
Kids Zone