Financial Number: 231440-2-52-01
Project Length: 1.8 miles
Project Limits: From just west of South 25th Street to just east of U.S. 1
Start Date: November 7, 2016
Completion Date: December 9, 2021
Contractor: Morrison-Cobalt JV
Estimated Construction Cost: $26.85 Million
Scope of Work: The improvements on this project included: reconstructing the existing two-lane Midway Road to a four-lane, divided highway with a raised median; installing a new signal at Sunrise Boulevard; constructing a new bridge over the North Fork St. Lucie River; constructing a 6-foot sidewalk on the north side and a 12-foot multi-purpose trail on the south side Midway Road; constructing 4-foot bike lanes on both sides of the roadway; reconstruction of S. 25th Street approximately 1000’ to the south & north of Midway Road; reconstruction of Sunrise Boulevard from W. 1st Street to Charlotta Street; reconstruction of Oleander Avenue from W. 2nd Street to Merritt’s Ditch; drainage improvements, including constructing 6 retention ponds at 5 locations; and signage, signalization, and lighting improvements.
Click here for upcoming lane closures |