Treasure Coast Header Image

I-95 Lighting and Roadway Improvements Project from South of the Martin County Rest Area to south of State Road 714 / Martin Highway

Financial Number: 437701-1-52-01

Project Length: 5 miles

Project Limits: From south of the Martin County Rest Area to south of SW Martin Highway (State Road 714)

Start Date: April 23, 2019

Estimated Completion Date: Summer 2020

Contractor: Ferreira Construction Co., Inc.

Estimated Construction Cost: $5,985,000.01

Scope of Work:
The improvements on this project include: installing lighting along I-95; lengthening the I-95 entrance ramp auxiliary lane from the Martin County northbound rest area; milling & resurfacing along northbound I-95 at the Martin County northbound rest area to tie into the reconstructed auxiliary lane; and milling & resurfacing of the existing pavement and placing overbuild along southbound I-95 where needed for cross slope corrections.

Click here for upcoming lane closures

 

Project Photos

Pre-Construction

Click to view enlarged version/details
Pre-construction Pre-construction Pre-construction Pre-construction
Pre-construction Pre-construction Pre-construction Pre-construction
Pre-construction Pre-construction

During-Construction

Click to view enlarged version/details
Pre-construction Pre-construction Pre-construction Pre-construction
Pre-construction Pre-construction Pre-construction
       

 

 

 

Please click on a link below to view construction projects
in other areas of Treasure Coast:
Martin County ProjectsMartin County St. Lucie CountySt. Lucie County Indian River CountyIndian River County
Florida Department of Transportation
Kids Zone
© 2014, Florida Department of Transportation District Four