Lighting Improvements Project in Coral Springs, Margate, Pompano Beach, Deerfield Beach and Fort Lauderdale

Financial Number: 440077-1-52-01, 440086-1-52-01, 440075-1-52-01 and 440076-1-52-01

Project Limits: Atlantic Blvd/SR 814 Sample Road/SR 834 University Drive/SR 817 Powerline Rd/SR 845 in Coral Springs, Margate, Pompano Beach, Deerfield Beach and Fort Lauderdale

Start Date: October 22, 2019

Completion Date: Early 2021

Contractor: PowerCore, Inc.

Estimated Construction Cost: $1.4 million

Scope of Work:
This project will take place along four major state roads: SR 817/University Drive, SR 834/Sample Road, SR 845/Powerline Road and SR 814/Atlantic Boulevard. The improvements will upgrade illuminations at signalized intersections with new light poles, new light fixtures and retrofit existing lighting fixtures with LED lights

PDF IconProject Flyer

PDF IconLighting Improvements Project Flyer

 

Click here for upcoming lane closures

 

Project Photos

During Construction

 

 




Please click on a link below to view construction projects
in other areas of Broward County:
I-95 Palm Beach CountyInterstates Northern Palm Beach CountyNortheast Western Palm Beach CountyNorthwest
I-95 Palm Beach CountySoutheast Northern Palm Beach CountySouthwest
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express