Financial Number: 434686-1-52-01
Project Limits: NE 11th Avenue from SR 814/Atlantic Boulevard to NE 6th Street; NE 48th Street/NE49th Street from SR 845/Powerline Road to SR 5/US 1; SE 2nd Avenue from SR 869/SE 10th Street to SR 810/Hillsboro Boulevard; SW 3rd Avenue from SR 869/SW 10th Street to SR 810/Hillsboro Boulevard
Start Date: July 12, 2019
Completion Date: Early 2021
Contractor: Roadway Construction, LLC
Estimated Construction Cost: $4.1 Million
Scope of Work: Project improvements in Pompano Beach include adding pavement markings and missing sidewalk on NE 11th Avenue. Project improvements in Deerfield Beach include milling and resurfacing NE 48th Street/NE 49th Street with minor widening to accommodate bike lanes in both directions, adding pavement markings on SE 2nd Avenue, and milling and resurfacing and adding pedestrian lighting on SW 3rd Avenue. Other improvements include curb and gutter, pavers and reconstructed driveways.