Financial Number: 441582-1-52-01 and 439991-1-52-01
Project Length: 2.5 miles
Project Limits: SR-5/US-1/Federal Highway from SR-824/Pembroke Road to SR-822/Sheridan Street
In-Person Construction Open House: Thursday, December 15, 2022, from 6 p.m. to 7 p.m. at the Fred Lippman Multi-Purpose Center, located at 2030 Polk Street, Hollywood, FL 33020.
Virtual Public Meeting: Thursday, December 15, 2022, from 5 p.m. to 6 p.m.
Start Date: January 2023
Completion Date: Early 2024
Contractor: AUM Construction, Inc.
Estimated Construction Cost: $7,152,129
Scope of work:
The project improvements consist of milling and resurfacing along the project limits, modifying pavement markings along SR-5/US-1/Federal Highway to accommodate 4-foot bicycle lanes in each direction, installing 138 new light poles and upgrading existing lighting to LED along the corridor, replacing concrete sidewalk with pavers from Monroe Street to Van Buren Street and from Polk Street to Fillmore Street, removing existing pavers at the signalized intersections between Van Buren Street and SR-824/Pembroke Road, and installing decorative stamped asphalt crosswalks at all signalized intersections.