SR 822/Sheridan Street Bridge Rehabilitation Project
Financial Number: 441462-1-52-01
Project Length: 900 ft
Project Limits: SR 822/Sheridan Street Bridge over the Intracoastal Waterway
In-Person Construction Open House: Wednesday, January 5, 2022, from 6 p.m. to 7 p.m. at the Hollywood Beach Culture & Community Center at 1301 S Ocean Drive, Hollywood, FL 33019.
Virtual Public Meeting: Thursday, January 6, 2022, from 5:30 p.m. to 6:30 p.m.
Start Date: January 22, 2022
Completion Date: Spring 2023
Contractor: PCL Construction, Inc.
Estimated Construction Cost: $12,200,214
Scope of Work: Project improvements include installing bicycle-friendly / anti-slip walking plates along the moveable spans, removing existing curb and adding a 4-foot traffic railing between the sidewalk and roadway, removing and replacing the outer pedestrian railing, adding new pedestrian gates in each direction, renovating the existing tender house, upgrading electrical and mechanical components, and access platforms on the bridge