Financial Number: 440043-1-52-01
Project Length: 0.1 mile
Project Limits: Brant Drive from Oregon Lane to Avocet Road
Start Date: August 2, 2021
Completion Date: Early 2023
Contractor: Cone & Graham, Inc.
Estimated Construction Cost: $2,472,960
Scope of Work: Work consists of replacing the two-lane Brant Drive Bridge (Bridge No. 935501) over the C-15 Canal with a new bridge consisting of two travel lanes and 10-foot shared-use paths in each direction. Improvements also include constructing 10-foot shared-use paths in each direction north of the bridge, reconstructing sidewalks south of the bridge, adding decorative lighting and drainage, upgrading signage and pavement markings, reconstructing roadway approaches and milling and resurfacing.