Financial Number: 440045-1-52-01
Project Length: 2.94 miles
Project Limits: Hall Boulevard from north of 72nd Court North to north of Temple Boulevard; Temple Boulevard from west of Hall Boulevard to west of 140th Avenue North; 140th Avenue North from north of 71st Place North to north of 82nd Street North
Start Date: October 2022
Completion Date: Spring 2023
Contractor: Heavy Civil, Inc.
Estimated Construction Cost: $928,650
Scope of Work: Work consists of constructing a raised median at the intersection of Hall Boulevard and Temple Boulevard, constructing two speed tables on Temple Boulevard, and installing six mid-block raised islands along Hall Boulevard and 140th Avenue North. Additional improvements include constructing asphalt sidewalks in select locations and upgrading pavement markings, signage and rumble strips.
Documents;
Indian Trail Improvement District Traffic Calming Project Notification
Point of Contact:
|