SR 9/I-95 Lighting & Safety Improvements Project from just south of Palm Beach Lakes Boulevard to just north of 45th Street

Financial Number: 445623-1-52-01

Project Length: 3.95 miles

Project Limits: SR 9/I-95 from south of Palm Beach Lakes Boulevard to north of 45th Street

Start Date: July 16, 2023

Completion Date: Early 2024

Contractor: Carr Construction, LLC

Estimated Construction Cost: $1.05 million

Scope of Work:

Project improvements include replacing the existing High-Pressure Sodium (HPS) roadway lighting with light-emitting diode (LED) roadway lighting along I-95 in both directions, installation of a Road Weather Information System (RWIS) on the I-95 southbound exit ramp to Palm Beach Lakes Boulevard, and installation of barrier delineators along the existing concrete median barrier walls.

Point of Contact:

 

Documents:

 

Pre-Construction

Click to view enlarged version/details
 
 
Please click on a link below to view construction projects
in other areas of Palm Beach County:
  I-95 Palm Beach CountyI-95 Construction Palm Beach County Northern Palm Beach CountyNorthern Palm Beach County
  Southern Palm Beach CountySouthern Palm Beach County Western Palm Beach CountyWestern Palm Beach County
  Central Palm Beach CountyCentral Palm Beach County Bridges Palm Beach CountyBridge Construction Palm Beach County
Florida Department of Transportation
Florida Department of Transportation
FDOT District Four Youtube
Kids Zone