Financial Number: 444477-1-52-01
Project Length: 3.349 miles
Project Limits: SR-A1A/SOUTH OCEAN BLVD FROM SOUTH OF GRAND CT TO SOUTH OF LINTON BLVD
Public Meeting:
The public meeting will take place on Monday, March 13, 2023, at 6:00 p.m.
The public meeting will be held at the Town of Highland Beach Library - Community Room, located at 3618 South Ocean Blvd, Highland Beach, Florida 33487.
To attend please register using the following link: http://bit.ly/3ILlDky.
The public meeting will be held in an open house format. Staff will be available to answer questions and provide assistance. If your question is not answered during the event, a response will be provided in writing following the meeting. Questions and comments may also be submitted prior to the meeting by emailing the Project Manager.
Projected Letting: December 2023
Start Date: Spring 2024
Completion Date: Summer 2025
Estimated Construction Cost: $8.8 M
Scope of Work:
- Resurface roadway pavement
- Minor widening to accommodate bicycles on the roadway shoulders
- Improve drainage in swales
- Upgrade signing and pavement markings to current standards
Construction Impacts:
- Work will be done in phases to reduce the effects of construction on the community
- Construction personnel will direct traffic during single lane closures to maintain two-way traffic
- Pedestrian and vehicular access to all properties will be maintained at all times
Contact Information:
Documents
SR-A1A from south of Grand Court to south of Linton Blvd - Flyer
SR-A1A from south of Grand Court to south of Linton Blvd - Presentation
SR-A1A from south of Grand Court to south of Linton Blvd - Roll Plot
|