Financial Number: 437717-1-52-01
Project Limits: 0.180 Miles
Project Length: CR-612/8th Street from west of 74th Avenue to east of Lateral Canal C
Start Date: June 5, 2023
Completion Date: Spring 2024
Contractor: Cone and Graham, Inc.
Estimated Construction Cost: $6.9 million
Scope of Work:
Project improvements consist of replacing the existing two-lane bridge (Bridge No. 884024) over Lateral Canal C, dredging Lateral Canal C to accommodate new bridge construction, installing guardrail to shield the canal hazards, and upgrading signing and pavement markings.
Click here for upcoming lane closures
Documents:
Lateral canal BridgeCR-612 Lateral Bridge Project Information Flyer
|