Project Limits: From Commerce Center Drive to Peacock Boulevard
Start Date: January 24, 2022
Completion Date: Late 2023
Contractor: Ranger Construction Industries, Inc.
Estimated Construction Cost: $15,518,729.37
Scope of Work: Project improvements include constructing a new 3-lane eastbound bridge over I-95, separated 10-feet from the existing bridge; widening St. Lucie West Boulevard to accommodate two (2) eastbound and westbound travel lanes, with a third eastbound lane between the I-95 southbound and northbound ramps, two (2) eastbound left turn lanes at the I-95 northbound on ramp, two (2) westbound right turn lanes at the I-95 northbound on ramp; reconstructing/widening the I-95 ramps; connecting the existing St. Lucie West Boulevard roadway to the new eastbound bridge from the east and west directions; constructing 7-foot buffered bike lanes/paved shoulder and 5-foot to 6-foot wide sidewalks on both sides of the roadway; constructing a 22-foot to 40-foot lane-line to lane-line curbed median with curb and gutter; installing fencing retrofits on the north side of the existing bridge, and new railing on the eastbound bridge; and, installing new traffic signals with enhanced synchronization and timing at I-95 ramps.