S.R. 824/PEMBROKE ROAD FROM OLEANDER DRIVE TO WEST OF SOUTH 61ST AVENUE

Financial Number: 446372‐1‐52‐01

Project Length: 2.05 Mile

Project Limits: From Oleander Drive to west of South 61st Avenue

Project Letting: Jul-23

Anticipated Start Date: Fall 2023

Anticipated Completion Date: Fall 2025

Estimated Construction Cost: $3.4 Million

Point of Contact:

Jamie Polidora, PE, PhD — FDOT Project Manager Phone: (954) 777-4633 Email: jamie.polidora@dot.state.fl.us

Scope of Work

  • Resurface and restripe roadway pavement Upgrade curb ramps to meet current standards Upgrade signs and pavement markings Upgrade existing signals at intersections Upgrade signalized intersection lighting with Light Emitting Diode (LED) luminaires Minor drainage improvements