Financial Number: 447555-1-52-01, 447555-2-52-01, 453333-3-52-01, 453333-2-52-01, 453333-1-52-01, 453333-4-52-01
Project Length: 17.745 miles FM 447555-1-52-01: 0.485 miles FM 447555-2-52-01: 0.356 miles FM 453333-3-52-01: 0.315 miles FM 453333-2-52-01: 9.812 miles FM 453333-1-52-01: 5.939 miles FM 453333-4-52-01: 0.838 miles
Project Limits: FM 447555-1-52-01: SR-710/SW WARFIELD BOULEVARD AT CR-714/SW MARTIN HIGHWAY FM 447555-2-52-01: SR-710/SW WARFIELD BLVD FR W OF SE 126 BLVD TO OKEECHOBEE/MARTIN CO LINE FM 453333-3-52-01: SR-710/SW WARFIELD BLVD FR W OF SE 126 BLVD TO OKEECHOBEE/MARTIN CO LINE FM 453333-2-52-01: SR-710 FROM MARTIN/OKEECHOBEE CO LINE TO FPL POWER PLANT ACCESS ROAD FM 453333-1-52-01: SR-710/SW WARFIELD BLVD FR FPL ACCESS RD TO SW ALLAPATTAH ROAD FM 453333-4-52-01: SR-710/SW WARFIELD BLVD FR SW ALLAPATTAH ROAD TO SW VAN BUREN AVE
Public Meeting: To Be Determined Link to registration page (to be determined)
Project Letting: FM 447555-1-52-01: 7/25/2029 FM 447555-2-52-01: 7/25/2029 FM 453333-3-52-01: 7/25/2029 FM 453333-2-52-01: Anticipated November 2030 FM 453333-1-52-01: Anticipated November 2030 FM 453333-4-52-01: 7/25/2029
Anticipated Start Date: To Be Determined
Anticipated Completion Date: To Be Determined
Estimated Construction Cost: $221.3 M FM 447555-1-52-01: 5.1M FM 447555-2-52-01: 13.1M FM 453333-3-52-01: 2.3M FM 453333-2-52-01: 126.2M FM 453333-1-52-01: 62.5M FM 453333-4-52-01: 12.1M