U.S. 27/State Road (S.R.) 25 Everglades Agricultural Area (EAA) Reservoir Inflow-Outflow Canal Bridges Project

Road Number: U.S. 27/S.R. 25

County: Palm Beach

Contract Number: T4736

Project Number: 448136-1-52-01

Project Length: 0.37 miles

Project Limits: Located 27 miles north of the U.S. 27/I-75 Interchange

Start Date: January 5, 2026

Completion Date: Fall 2028

Contractor: Prince Contracting, LLC

Estimated Construction Cost: $20.9 million

Point of Contact:

Kevin Wells — Community Outreach Specialist

Phone: 728-235-7218, Email: kevin@holtcommunications.net

Scope of Work

Project Improvements:

• Dredging a new canal in partnership with South Florida Water Management District for future connection to the EAA reservoir.
• Constructing northbound and southbound U.S. 27/S.R. 25 bridges over the South Florida Water Management District canal to facilitate enhanced stormwater resiliency.
• Milling and repaving the roadway throughout the project limits to enhance infrastructure resilience and safety.
• Constructing drainage and roadside swales for stormwater treatment and storage.
• Installing guardrail and concrete barrier walls to enhance motorist safety.
• Upgrading signage and pavement markings to enhance visibility and safety.