SR-9/I-95 at Palm Beach Lakes Boulevard Interchange Modification Project

Road: SR-9

Financial Number: 413260-01-52-01

Project Length: 1.363 mile

Project Limits: Palm Beach Lakes Boulevard from North Robbins Drive East to East Mall Entrance

Public Meeting: <p>The in-person meeting will take place on<br /> Thursday, May 28, 2026, at 6:00 p.m. at the<br /> Okeechobee Boulevard Branch Library,<br /> 5689 Okeechobee Boulevard, West Palm Beach, FL 33407</p>

Project Letting: 3/31/2027

Anticipated Start Date: Fall 2027

Anticipated Completion Date: Spring 2029

Estimated Construction Cost: $13.7 Million

Point of Contact:

Vamsee Tirunagari, P.E.
FDOT District 4 – In-House Consultant Project Manager
3400 W Commercial Blvd.
Fort Lauderdale, Florida 33309
Phone: (954) 777-4061
Email: vamsee.tirunagari@dot.state.fl.us

Project Purpose

The main purpose of the project is to address future traffic impacts at the SR-9/I-95 Interchange at Palm Beach Lakes Boulevard.

Scope of Work

• Mill and resurface the existing asphalt pavement within the project limits
• Widening Palm Beach Lakes Blvd to add auxiliary lanes. and the I-95 off ramps to provide additional turn lanes.
• Address drainage impacts due to widening.
• Replace lighting and Signal mast arms/span wire assemblies impacted by the widening.
• Upgrade existing pedestrian curb ramps and install detectable warning surfaces.
• Lighting retrofit at the signalized intersections and replace existing luminaires with LED luminaires on the two off-ramps.
• Signing & Pavement Marking improvements including replacing existing OH cantilever signs with new OH Span signs
• ITS improvements include two new ADMS.

Construction Impacts

• Work will be done in phases to reduce the  effects of construction on the community.
• Vibration and noise from construction activity.
• Temporary lane closures to build the improvements will be completed during non-peak hours
• Pedestrian and vehicular access to all properties will always be maintained