Road: S.R. 9
Local Road Name: I-95
City: Pompano Beach
County: Broward
Financial Number: 451043-1-52-01
Project Length: 1.554 miles
Project Limits: Mile Post 4.434 to Mile Post 5.363
Project Letting: January 8, 2027
Anticipated Start Date: Spring 2027
Anticipated Completion Date: Winter 2027
Estimated Construction Cost: $1,394,184
Haiyan Ou, P.E.
954-777-4641
haiyan.ou@dot.state.fl.us
The purpose of this project is to increase the beautification of the I-95 interchange following the previous tree disposition project. Additional beautification is achieved through the installation of additional trees and palm within the interchange as well as landscaping the open Copans Road medians with shrubs, trees, and palms.
Landscape revitalization will primary address the I-95 and Copans Road interchange. Landscaping throughout the interchange will include a mix of palms, flowering trees, and canopy trees. Additional improvements will be made to the Copans Road medians to add landscape and irrigation.
Minimal impacts on the public are anticipated. No lane closures or detours along I-95 or the interchange ramps are anticipated. Shoulder closures may be required to protect the workers. Temporary lane closures adjacent to the Copans Road medians will take place during non-peak hours.