State Road (S.R.) 5/U.S. 1 at Baker Road, Northwest North River Shores Boulevard, and Northwest Sunset Boulevard

Road: S.R. 5

Local Road Name: U.S. 1

City: Stuart and Unincorporated

County: Martin

Financial Number: 444415-1-52-01, 444416-1-52-01, and 444417-1-52-01

Project Length: .228

Project Limits: at Baker Rd, at NW North Rivershores Blvd., at NW Sunset Blvd.

Project Letting: 12/2/2026

Anticipated Start Date: Spring 2027

Anticipated Completion Date: Spring 2028

Estimated Construction Cost: 4.2 million

Point of Contact:

Damaris Williams, P.E.

Project Manager, FDOT District 4
Office: 954-777-4679
damaris.williams@dot.state.fl.us

Project Purpose

To enhance safety by upgrading the intersections with mast arms and other safety improvements

project maps

444415-1-52-01

444416-1-52-01

444417-1-52-01

Project Improvements

  • Replace existing signalization strain pole systems with mast arms.
  • Upgrading pedestrian signals and detectors.
  • Upgrading the existing intersection lighting.
  • Replacing and upgrading existing curb ramps to comply with Americans with Disabilities Act (ADA) standards.
  • Repaving the existing roadway within the intersections.
  • Upgrading signing and pavement markings.
  • Adding a 11-foot-wide northbound right turn lane on S.R. 5/U.S. 1 and Baker Road intersection.
Example Mast Arm

Example of a Mast Arm

Example Pedestrian Signal

An Example of a Pedestrian Signal

Light pole example

Example of a Light Pole

Construction Impacts

  • All work will be done in phases to reduce the impacts of construction on the community.
  • Temporary lane closures will be required during construction. Lane closures will be performed at off-peak hours.
  • Pedestrian and vehicular access to all businesses and residential properties will be maintained at all times during construction.