State Road (S.R.) 838/W Sunrise Boulevard

449821-1 SR-838/W Sunrise Boulevard Project Map

Road: S.R. 838

Local Road Name: W. Sunrise Boulevard

City: Plantation, Lauderhill, and Fort Lauderdale

County: Broward

Financial Number: 449821-1-52-01

Project Length: 1.023 miles

Project Limits: NW 47th Avenue to west of the SR-9/I-95 Overpass

Project Letting: September 29, 2027

Anticipated Start Date: Fall 2027

Anticipated Completion Date: Fall 2029

Estimated Construction Cost: $7.1 million

Point of Contact:

FDOT Project Manager Haiyan Ou, P.E.
(954) 777-4641
Haiyan.Ou@dot.state.fl.us

Consultant Project Manager Allan Sequeira, P.E.
(786) 885-0097
Allan.Sequeira@bargedesign.com

Meetings

A Public Meeting will be held on Thursday, October 29, 2026, at 6:00pm
Location: Reverend Samuel Delevoe Memorial Park
2520 NW 6th Street
Fort Lauderdale, FL 33311

Project Purpose

The purpose of this project is to preserve and extend the service life of the existing pavement through milling and resurfacing along this section of SR-838/Sunrise Boulevard in Broward County.

Project Improvements

The Scope of Work includes milling and resurfacing the existing roadway to ensure a smooth, safe, and resilient drive. Crews will upgrade signalization, install pedestrian signal upgrades, and bring sidewalk and curb ramps to meet Americans with Disabilities Act (ADA) requirements. Signs and pavement markings will be replaced and upgraded to meet current standards and increase reflectivity.

Construction Impacts

Adjacent businesses and residential communities may have concerns about construction activities for the proposed project. Construction may generate air, noise, vibration, water quality, and visual impacts of a temporary nature for residents and travelers within the immediate vicinity of the project area. Maintenance of traffic issues will be a key concern once construction activities begin. Access and safety will be priorities. A Traffic Control Plan (TCP) will be developed for this project in accordance with current FDOT and FTE requirements prior to the start of construction. The TCP will address traffic control measures and phasing to minimize disruptions to traffic operations during construction to the extent possible.