Financial Number: 441570-1-52-01
Project Length: 1.060 miles
Project Limits: 36th Street from North Australian Avenue to North Flagler Drive
Public Meeting: <p>The in-person public meeting will be held<br /> Thursday, April 30, 2026 at 6:00 p.m., at: </p> <p>Grace Episcopal Church<br /> Parrish Room<br /> 3600 North Australian Avenue<br /> West Palm Beach FL 33407″</p>
Project Letting: January 2027
Anticipated Start Date: Summer 2027
Anticipated Completion Date: Spring 2029
Estimated Construction Cost: 15.8 Million
Jeffrey Robbert, P.E. – FDOT Project Manager
Florida Department of Transportation
3400 West Commercial Boulevard
Fort Lauderdale, FL 33309
Phone: (954) 777-4648
Email: jeffrey.robbert@dot.state.fl.us
To enhance pedestrian and bicyclist mobility, and improve safety along the corridor.
• Repave 36th Street from North Australian Avenue to North Flagler Drive.
• Provide shared-use paths and sidewalks.
• Provide bicycle lanes within project limits.
• Replace existing bridge #937704 over Carver Canal with a new 102’ bridge.
• Upgrade sidewalks and curb ramps to comply with Americans with Disabilities Act (ADA).
• Install pedestrian lighting within project limits.
• 36th Street will remain closed for vehicular traffic, from Australian Avenue to Townhouse Court, during bridge construction.
• Detours for vehicular traffic will be provided. Pedestrian access across Carver Canal will be maintained at all times.
• Roadway work will be done in phases to reduce the effects of construction on the community.
• Temporary lane closures to build the improvements will be completed during non-peak hours
• Pedestrian and vehicular access to all properties will always be maintained.