SR-9/I-95 @ PGA Boulevard/Central Boulevard from North of Military Trail to South of Donald Ross

Road: S.R. 9

Local Road Name: I-95

City: Palm Beach Gardens

County: Palm Beach

Financial Number: 413265-1-52-01

Project Length: 2.861 miles

Project Limits: From north of Military Trail (MP 37.206) to south of Donald Ross Road (MP 40.067)

Project Letting: Spring 2028

Anticipated Start Date: Fall 2028

Anticipated Completion Date: Fall 2033

Estimated Construction Cost: $108 million

Point of Contact:

Bing Wang, P.E. – Project Manager

Phone: (954) 777-4482
Bing.Wang@dot.state.fl.us

Project Purpose

Improve operational capacity and overal traffic operations.

Project Improvements

Proposed Improvements:
• New diamond interchange at I-95 and Central Boulevard
• I-95 pavement resurfacing and widening from Military Trail to Donald Ross Road
• Collector Distributor roadways between Military Trail and Central Boulevard
• Widen existing Central Boulevard bridge
• Construct 10-foot wide Shared Use Path along the south side of Central Boulevard
• Upgrade lighting, signing and pavement markings
• Install signalization, ITS and Wrong Way Detection devices

Construction Impacts

Traffic control will affect motorists, bicyclist, pedestrians, and construction personnel for the duration of construction. The following traffic control related items are anticipated:
• Temporary lane closures – the project plans attempt to minimize the impacts to motorists due to lane closures. Lane closures will occur during off-peak hours.
• Scheduling of activities – construction activities will be reviewed with consideration of the time of letting, restricted work hours, workday duration, nighttime operations, weekend work, and holiday restrictions.