DRAG
img

Search here

State Road (S.R.) 5/U.S. 1 at Southwest Joan Jefferson Way Intersection Improvement Project – 438345-2-52-01

Road: S.R. 5

Financial Number: 438345-2-52-01

Project Length: 0.029 mile

Project Limits: S.R. 5/ U.S. 1 at Southwest Joan Jefferson Way

Project Letting: Winter 2028

Anticipated Start Date: Spring 2028

Anticipated Completion Date: Fall 2028

Estimated Construction Cost: $1.5M

Point of Contact:

Leslie Wetherell, P.E., Project Manager
Phone: (954) 777-4438
leslie.wetherell@dot.state.fl.us

Scope of Work

  • Replace the existing signal mast arms.
  • Provide queue detection camera for Southwest Joan Jefferson Way eastbound traffic.
  • Reconstruct concrete curb ramps to comply with American with Disabilities Act (ADA) standards.
  • Repave and restripe the intersection.
  • Remove existing brick crosswalk pavers and replace with new pavement.
  • Upgrade the existing intersection lighting.

Construction Impacts

  • All work will be done in phases to reduce the impacts of construction on the community.
  • Sidewalk detours will be provided to maintain safe pedestrian access during construction.
  • Temporary lane closures will occur during non-peak hours to minimize impacts on traffic.

Useful Links

// Image Grid Start 20h March // Image Grid Eng 20h March