State Road S.R. A1A from Sheridan St. to E. Dania Beach Blvd

Road: A1A

City: Hollywood

County: Broward

Financial Number: 448402-1-52-01

Project Length: 1.228 miles

Project Limits: Sheridan Street to East Dania Beach Boulevard

Project Letting: 8/25/2027

Anticipated Start Date: Winter 2027

Anticipated Completion Date: Winter 2028

Estimated Construction Cost: $2 million

Point of Contact:

Vandana Nagole, PE
954-777-4281
Vandana.Nagole@dot.state.fl.us

Meetings

Thursday, September 17, 2026, at 5:00 p.m.

State Road S.R. A1A from Sheridan St. to E. Dania Beach Blvd meeting location map

Anne Kolb Nature Center
751 Sheridan Street
Hollywood, Florida 33019

To participate in the virtual public meeting from your computer, tablet, or smartphone please register using the following link or QR code below:
https://tinyurl.com/3RSRA1A
Participants can also dial in using their phone:
Dial in number: +1 (562) 247-8422
Access code: 547-845-386

 

Project Purpose

Repave and restripe the existing roadway to extend the service life of the pavement, enhance safety for motorists, pedestrians and bicyclists.

Project Improvements

  • Repave the existing roadway to improve the resiliency of our infrastructure.
  • Widen the roadway pavement 3 feet on both sides to provide seven feet buffered bike lanes to better accommodate cyclists who wish to use the roadway.
  • Replace areas of deteriorated pavement to improve safety for motorists.
  • Modify curb ramps to comply with the Americans with Disabilities Act (ADA) to facilitate improved access for users with disabilities.
  • Replace and upgrade signs and pavement markings to meet current standards and increase reflectivity.

Construction Impacts

  • Work will be done in phases to reduce the effects of construction on the community.
  • Flagging operations will be in place while repaving and detours will be utilized while areas of deteriorated pavement are replaced.
  • Access to businesses and residences will be maintained during construction.
  • Another public meeting (Construction Open House) will be held prior to construction. Detailed information about how to keep informed of potential construction impacts will be provided at that meeting.