U.S. 27 Corridor & I-75 Bridge Improvements

Road: U.S. 27, S.R. 25, S.R. 818, I-75, S.R. 93

Local Road Name: Griffin Road

County: Broward

Financial Number: 449819-1-52-01, 449819-1-52-02, 449819-1-52-03, 449819-1-52-04, 449819-2-52-01, 452921-1-52-01, 452942-1-52-01

Project Length: 8.170 miles

Project Limits: U.S. 27/State Road (S.R.) 25 from North of S.R. 818/Griffin Road to North of Sawgrass Recreation Park as well as I-75/S.R. 93 Over Glades Parkway

Project Letting: March 2027

Anticipated Start Date: Fall 2027

Anticipated Completion Date: Summer 2029

Estimated Construction Cost: $48 Million

Point of Contact:

Smiley Urena P.E., PTOE – FDOT Project Manager
Florida Department of Transportation
3400 West Commercial Boulevard,
Fort Lauderdale, Florida 33309

Phone: (954) 777-4462 or Toll Free (866) 336-8435 Ext. 4462
Email: Smiley.Urena@dot.state.fl.us

 

Meetings

In-Person and Virtual Public Meeting  Meeting Location map: Weston City Hall Commission Chambers 17200 Royal Palm Blvd. Weston, Fl 33326

Wednesday, June 17, 2026, at 6:00 p.m.
Weston City Hall – Commission Chambers
17200 Royal Palm Boulevard, Weston, Florida 33326

 

To participate in the virtual public meeting from your computer, tablet, or smartphone please register using the following link https://qr.link/0UFygC or scan the QR code below:


Participants can also dial in using their phone:
Dial in number: +1 (415) 655-0052
Access code: 205- 468 – 498

Project Purpose

This project will improve safety, access and traffic flow.

Project Improvements

• Repaving and re-striping the existing roadway.

• Constructing a 10-ft paved shoulder from north of Griffin Road to north of the Seminole Travel Center/Marathon Gas truck stop.
• Adding a southbound left turn lane and northbound right turn lane into the Seminole Travel Center/Marathon Gas truck stop.
• Widening of the bridge over the C-11 canal.
• Replacement and upgrading of signage impacted by construction.
• Replacement and upgrading of the existing lighting north of Griffin Road.
• Repair of I-75 bridges over U.S. 27 and Glades Parkway.
• Intelligent Transportation Systems technology devices will be upgraded along U.S. 27.

Construction Impacts

• Work will be done in phases to reduce the impacts to the community.
• Temporary detours and lane closures will be required.
• Access to properties along the corridor will be maintained during construction.
• Daytime and nighttime lane closures are expected for this project.