S.R. 9/I-95 Ramp Improvements Project

S.R. 9_I-95 Ramp Improvements Project

Road: State Road 9

City: West Palm Beach

County: Palm Beach

Financial Number: 453144-1-52-01

Project Length: 2.283

Project Limits: RAMP 1: SOUTHBOUND I-95 OFF-RAMP TO PRESIDENT DONALD J. TRUMP INTERNATIONAL AIRPORT // RAMP 2: SOUTHBOUND I-95 ON-RAMP FROM WESTBOUND S.R. 704/OKEECHOBEE BLVD. // RAMP 3: SOUTHBOUND I-95 ON-RAMP FROM WESTBOUND S.R. 706/INDIANTOWN ROAD

Project Letting: March 2027

Anticipated Start Date: Fall 2027

Anticipated Completion Date: Fall 2028

Estimated Construction Cost: 3.5 Million

Point of Contact:

Vamsee Tirunagari, P.E.
District 4 – In-House Consultant Project Manager
3400 W Commercial Blvd.
Fort Lauderdale, Florida 33309
Email: vamsee.tirunagari@dot.state.fl.us
Phone: (954) 777-4061

Project Purpose

  • To provide safety improvements along three I-95 ramps.

Project Improvements

  • Repave and restripe the three Interstate ramps to improve the driving surface.
  • Install a high-friction surface treatment to enhance traction and improve safety.
  • Replace and upgrade signs and pavement markings to meet current standards and increase reflectivity.

Construction Impacts

  • Construction will occur one ramp at a time.
  • Temporary traffic detours will be in place.
  • Seasonal and holiday traffic will be considered during construction.
  • Access to and from I-95 will always be maintained during construction via short term nightly detours.
  • A subsequent construction flyer will be distributed prior to the start of construction. That flyer will provide detailed information on how to remain informed about potential construction impacts.