Financial Number: 451598-1-52-01
Project Limits: I-95 Northbound and Southbound Exit Ramps at SR-80/Southern Blvd I-95 Northbound Exit Ramp at Congress Avenue / Peninsula Court I-95 Northbound Exit Ramp at SR-794/Yamato Road
Anticipated Start Date: Fall 2026
Anticipated Completion Date: Fall 2027
Estimated Construction Cost: $1.5 million
Project Purpose: This project will install a Wrong Way Driving Detection System at four I-95 Interchange exit ramps. The detection systems will flash DO NOT ENTER signs to the driver and alert the Regional Transportation Management Center when a wrong way driver is detected.
Construction Impacts:
Temporary lane closures will occur during off-peak hours. Detours are required, one night per ramp, due to ramp closures for testing purposes. Pedestrian detours may be required for sidewalk closures.
Jeffrey Robbert, P.E. FDOT Project Manager Florida Department of Transportation 3400 West Commercial Boulevard Fort Lauderdale, FL 33309 Phone: (954) 777-4648 Email: jeffrey.robbert@dot.state.fl.us