Financial Number: 450587-2-52-01
Project Length: 0.86 miles
Project Limits: CR 707/Dixie Highway Bridge (Old Roosevelt Bridge) Bridge #890003 over St. Lucie River
Public Meeting: <p>Tuesday, September 16, 2025,(5:30 p.m. – 7:00 p.m.) Link to registration page: https://register.gotowebinar.com/register/5366990481617423962</p>
Project Letting: Summer 2026
Anticipated Start Date: Fall 2026
Anticipated Completion Date: Spring 2028
Estimated Construction Cost: $11 Million
Work will be done in phases to reduce the effects of construction on the community Full and partial bridge closures will occur only during specific phases and detours will be provided utilizing US-1. Temporary lane closures will be required for some phases (such as minor repaving) and will occur during non-peak hours. Marine vessel traffic will be maintained with temporary closure on half the channel during fender construction. Another public meeting (Construction Open House) will be held prior to construction. Detailed information about how to keep informed of potential construction impacts will be provided at this meeting. Temporary modification to the draw bridge operation schedule will be coordinated with the United States Coast Guard.