Financial Number: 438386-4-52-01
Project Length: 15.399 miles
Project Limits: Proposed improvements include fourteen bus shelters located in Palm Beach County along SR 5/US 1, starting in the City of Boca Raton at Northeast 20th Street, and ending in West Palm Beach at Northlake Boulevard.
Project Letting: 01/28/26.
Anticipated Start Date: Spring 2026
Anticipated Completion Date: Spring 2027
Estimated Construction Cost: $5.1 M
Sara Hernandez Arias, P.E. – FDOT Project Manager Phone: (954) 777-411 Email: sara.hernandezarias@dot.state.fl.us
Work will be done in phases to reduce the impacts to the community and access to businesses and residences will be maintained during construction. Temporary lane closures will occur one lane at a time during non-peak hours to minimize impacts on traffic and pedestrian traffic will be maintained at all times. Temporary bus stops will be provided for existing bus shelter impacts.