Financial Number: 454564-1-52-01
Project Length: 0.405 miles
Project Limits: SR 706/Indiantown Road from 67th Road North to Palm Road
Public Meeting: <p>Virtual Meeting: Tuesday, September 30, 2025, from 5:00 p.m. – 6:00 p.m. To participate in the virtual public meeting from your computer, tablet or smartphone please register using the following link: https://tinyurl.com/d2j8yuyz In-person Meeting: Tuesday, September 30, 2025, from 6:00 p.m. – 7:00 p.m. at the Jupiter Community Center located at 200 Military Trail, Jupiter, Florida 33458</p>
Project Letting: May-26
Anticipated Start Date: Fall 2026
Anticipated Completion Date: Fall 2027
Estimated Construction Cost: $2.75 M
Jeffrey Robbert, P.E. — FDOT Project Manager Phone: (954) 777-4648 Email: Jeffrey.Robbert@dot.state.fl.us
Work will be done in phases to reduce the impacts to the community Temporary lane closures will be required to construct the roadway widening Pedestrian traffic will be maintained at all times Access to properties along the corridor will be maintained during construction