Financial Number: 437279-1-52-01
Project Length: 1.697 Miles
Project Limits: State Road (SR) 9/I-95 Interchange at Woolbright Road from south of Woolbright Road to north of Woolbright Road
Anticipated Start Date: Fall 2026
Anticipated Completion Date: Summer 2029
Estimated Construction Cost: $22 million
Mr. Humberto Arrieta, P.E. – FDOT Project Manager Phone: (954) 777-4152 Email: Humberto.Arrieta@dot.state.fl.us
The public meeting was offered virtually and in-person. The virtual public meeting took place on Wednesday, March 8, 2023, at 6:00 p.m. and was held via GoToWebinar. The in-person public meeting followed an open house format and took place on Thursday, March 9, 2022, from 6:00 p.m. to 7:30 p.m. and was held at the Boynton Beach City Hall located at 100 East Ocean Avenue (Room – MR 115), Boynton Beach, FL 33435. Staff was available to answer questions and provide assistance.
To improve operations and safety within the interchange.
Work will be done in phases to reduce the inconvenience to the community Lane closures, ramp closures, and detours will occur during non-peak hours to minimize impacts on traffic Access to businesses and residential properties will be maintained at all times during construction