95 Express Phase 3C, I-95 from south of Hollywood Boulevard to south of Broward Boulevard

Road: I-95

Areas: Interstates

Project Number: 409354-2-52-01, 432222-1-52-01

Project Length: 9 miles

Project Limits: I-95 from south of Hollywood Boulevard to south of Broward Boulevard & I-595 from west of S.R.-7 to I-95

Start Date: January 2019

Completion Date: Early 2026

Contractor: Archer Western Construction, LLC & The deMoya Group, Inc.

Estimated Construction Cost: $457,000,000

Point of Contact:

Daniela Silva, Community Outreach Specialist, Phone: (786) 441-3088, Email: msilva@corradino.com

Scope of Work

  • Reconstruction, milling, resurfacing, overbuild, widening, and/or restriping of I-95 from south of Hollywood Boulevard to south of Broward Boulevard to accommodate the following:
  • One additional Express Lane in each direction (2 lanes total in each direction), between south of Stirling Road and Broward Boulevard.
  • A southbound Express Lanes entrance and a northbound Express Lanes exit location, serving Sheridan Street and interchanges to the north for traffic to and from the south.
  • A northbound Express Lanes entrance and a southbound Express Lanes exit location, serving Sheridan Street and interchanges to the south for traffic to and from the north.
  • Construction of dual exits for the northbound and southbound exit ramps to Sheridan Street.
  • Dual right turn lane improvements at the ramp terminal for the I-95 northbound exit ramp movement to eastbound Griffin Road.
  • I-95/I-595 Direct Connectors between northbound and southbound 95 Express Lanes and I-595, to and from the west.
  • I-95/S.R. 84 Interchange modifications, including replacement of the westbound SR 84 bridge over I-95, to accommodate one additional Express Lane in each direction along I-95 and Direct Connectors to and from I-595.
  • Reconstruction, milling, resurfacing, overbuild, widening, and/or restriping of I-595 from S.R. 7 to I-95, including the I-595 bridges of Pond Apple Slough, to accommodate the following:
  • Additional auxiliary lanes along I-595 and to/from the Direct Connectors.
  • A new westbound I-595 exit ramp to Turnpike.
  • A new eastbound I-595 entrance ramp from Turnpike.
  • A new eastbound I-595 exit ramp to eastbound S.R. 84.
  • Other work includes bridge widening, bridge painting, ITS, Tolling/gantry, signage, ramp signalization, lighting, drainage, shoulder mounted sound walls, and retaining walls.