S.R. 804/Boynton Beach Boulevard Resurfacing, Restoration, and Rehabilitation Project

Road Number: S.R. 804/Boynton Beach Boulevard

Contract Number: E4X90

Project Number: 448437-1-52-01

Project Length: 0.595 miles

Project Limits: State Road (S.R.) 804/ Boynton Beach Boulevard from east of Orchid Grove Trail to Palm Isles Drive

Start Date: January 22, 2026

Completion Date: Fall 2026

Contractor: Weekley Asphalt Paving, Inc

Estimated Construction Cost: $2.7 million

Point of Contact:

Kevin Wells, Community Outreach Specialist

Phone: (728) 235-7218, Email: kevin@holtcommunications.net

Scope of Work

Project Improvements:

  • Milling and repaving the roadway throughout the project limits to enhance infrastructure resilience and improve safety for the community.
  • Upgrading curb ramps and replacing sections of the existing sidewalk to improve pedestrian safety and connectivity.
  • Reconstructing and realigning median sections to enhance traffic flow.
  • Upgrading pedestrian signals with new LED countdowns at Hagen Ranch Road and Palm Isles Drive to enhance pedestrian use.
  • Upgrading signage and pavement markings, including installing green bicycle markings, to enhance visibility and safety.