Road Number: S.R. A1A
Contract Number: T4727
Project Number: 447650-1-52-01
Project Length: 2.277 miles
Project Limits: SR A1A from NE Shore Village Ter to SR 732/Jensen Beach Causeway
Start Date: Spring 2026
Completion Date: Spring 2026
Contractor: INC USA Corporation
Estimated Construction Cost: $4,898,324
Kim Johnson — Community Outreach Specialist
Kim@holtcommunications.net or (772) 801-8736
PROJECT IMPROVEMENTS
• Milling and resurfacing of S.R. A1A/NE Ocean Boulevard to extend the service life of the road to provide long term resiliency
• Installing new drainage structures to improve stormwater management
• Widening the shoulders to increase width to five-feet at select locations
• Upgrading the existing lighting at the Jensen Beach Causeway roundabout
• Upgrading of pedestrian curb ramps to comply with American with Disabilities Act (ADA) standards for improved safety and connectivity
• Installation of traffic calming measures and speed feedback signs