State Road (S.R.) 15/E Main Street Resurfacing, Restoration and Rehabilitation (RRR) Project

Road Number: S.R. 15/E Main Street

Contract Number: T4719

Project Number: 447664-1-52-01

Project Length: 3.342 miles

Project Limits: S.R. 15/E Main Street from Annona Street to south of S.R. 700/Conners Highway

Start Date: November 3, 2025

Completion Date: March 6, 2026

Contractor: General Asphalt Company, LLC

Estimated Construction Cost: $3.5 million

Point of Contact:

Kevin Wells, Community Outreach Specialist

Phone: 728-235-7218, Email: kevin@holtcommunications.net

Scope of Work

Project Improvements:

  • Milling and repaving the existing roadway within the project limits to ensure long-term infrastructure resiliency and safety.
  • Constructing six concrete bus pads throughout the project corridor to enhance transit rider safety and accessibility.
  • Installing curb ramps and replacing sections of sidewalk to enhance pedestrian safety and connectivity.
  • Upgrading signage and pavement markings, including bicycle lane markings, to enhance visibility and safety.