State Road (S.R.) 806/Atlantic Avenue and Homewood Boulevard Intersection and S.R. 704/Okeechobee Boulevard and Haverhill Road Intersection Improvements Project

Road Number: S.R. 806 and S.R. 704

County: Palm Beach

Contract Number: T4707

Project Number: 449283-1-52-01

Project Length: 0.4 miles

Project Limits: S.R. 806/Atlantic Avenue and Homewood Boulevard Intersection and S.R. 704/Okeechobee Boulevard and Haverhill Road Intersection

Start Date: October 2025

Completion Date: July 30, 2026

Contractor: Weekley Asphalt Paving, Inc.

Estimated Construction Cost: $3.2 Million

Point of Contact:

Ricky Estripeaut, P.E.— FDOT Project Manager

Ricky.Estripeaut@dot.state.fl.us or (561) 370-1132

Diana Bermudez — Project Administrator

Diana.Bermudez@dot.state.fl.us or (561) 978-4692

Kevin Wells — Community Outreach Specialist

Kevin@holtcommunications.net or (728) 235-7218

Scope of Work and Project Improvements

  • Replacing existing traffic signals with mast arms at each intersection to improve infrastructure resiliency and enhance motorist safety.
  • Extending the eastbound and westbound left turn lanes from SR 806/Atlantic Avenue to Homewood Boulevard and High Point Boulevard to improve traffic flow.
  • Extending the eastbound left turn lane from SR 704/Okeechobee Boulevard to N Haverhill Road to improve traffic flow.
  • Upgrading pedestrian signals with new LED countdown timers to enhance pedestrian use.
  • Upgrading curb ramps and replacing sections of the existing sidewalk throughout the project limits to enhance pedestrian safety and connectivity.
  • Installing new LED lighting at the SR 806/Atlantic Avenue and Homewood Boulevard intersection to improve nighttime visibility for all roadway users.
  • Repaving and minor widening along Homewood Boulevard to improve bicycle and roadway facilities.

Traffic Impacts

  • Work will occur in phases to minimize impacts to the public.
  • Lane closures are permitted nightly from 9:00 p.m. until 7:00 a.m.
  • Sidewalk and curb ramp closures will be implemented as needed with temporary pedestrian detours.

 