State Road (S.R.) 838/Sunrise Boulevard at S.R. 9/I-95 Interchange Improvements and Resurfacing, Restoration, and Rehabilitation (RRR) Project

Road Number: S.R. 838

Contract Number: T4705

Project Number: 435516-1-52-01, 447678-1-52-01/02

Project Length: 2.3 miles

Project Limits: From S.R. 9/I-95 to S.R. 5/US 1

Start Date: June 2025

Completion Date: Early 2029

Contractor: GLF Posillico JV

Estimated Construction Cost: $55,449,488

Point of Contact:

Matthew May, P.E. — FDOT Construction Project Manager
matthew.may@dot.state.fl.us or
(954) 649-3220

Daniel Menendez, P.E. — Senior Project Engineer
daniel.menendez@atkinsrealis.com or
(305) 297-3600

Rey Jorge, P.E. — Project Administrator
rey.jorge@atkinsrealis.com or
(305) 282-3463

Trisha Rangil — Community Outreach Specialist
trisha.rangil@exp.com or
(754) 283-2929

Scope of Work and Project Improvements

 

  • Project improvements consist of widening S.R. 838/Sunrise Boulevard at the S.R. 9/I-95 Interchange overpass to accommodate dual right turn lanes onto northbound and southbound S.R. 9/I-95 to improve vehicular capacity and operations
  • Widening the southbound S.R. 9/I-95 (Exit 29) off-ramp to accommodate triple left and triple right turn lanes onto SR 838/Sunrise Boulevard to improve vehicular capacity and operations
  • Milling and resurfacing the existing roadway within the project limits to ensure long-term infrastructure resilience
  • Installing new light poles with LED fixtures at the S.R. 9/I-95 Interchange to enhance nighttime visibility
  • Installing Wrong-Way Driver detection systems on all ramps at the S.R. 9/I-95 Interchange to improve vehicular safety
  • Upgrading existing signalization features to improve pushbutton accessibility and enhance pedestrian safety
  • Adding a shared-use path on the S.R. 838/Sunrise Boulevard bridge over S.R. 9/I-95 to enhance pedestrian connectivity
  • Upgrading sidewalk curb ramps, pavement markings, and signage to enhance visibility and accessibility.

Traffic Impacts

  •  Lane closures along S.R. 838/Sunrise Boulevard are permitted, as
    needed, weeknights, 9:00 p.m. until 7:00 a.m., and are restricted
    to one direction at a time.
  • The inside lane for northbound and southbound S.R. 9/I-95
    Express will be closed during bridge foundation activities. The
    outside Express lane for northbound and southbound S.R. 9/I-95
    Express will remain open during this phase.
  •  Lane closures on S.R. 9/I-95 ramps are permitted, as needed, for
    roadway widening, Sunday to Thursday, 9:00 p.m. until 7:00 a.m.
  •  Full closures of the S.R. 9/I-95 mainline and ramps with detours
    are permitted, as needed, to set bridge beams and sign structures, Sunday to Thursday, 9:00 p.m. until 7:00 a.m.
  • Detours at NW 8th Avenue, NW 7th Avenue, and NE 4th Avenue
    will occur, as needed, for roadway and pavement reconstruction,
    weeknights, 9:00 p.m. until 7:00 a.m.
  •  Motorist and pedestrian access to businesses and residences will
    be maintained at all times.