State Road (S.R.) 9/I-95 Ramps Safety Improvement Project at S.R. 704/Okeechobee Boulevard, S.R. 786/PGA Boulevard, and S.R. 706/Indiantown Road

Road Number: S.R. 9/I-95

Contract Number: T4720

Project Number: 449280-1-52-01

Project Length: 0.902 miles

Project Limits: S.R. 704/Okeechobee Boulevard eastbound to I-95 northbound; I-95 northbound to S.R. 786/PGA Boulevard westbound; I-95 northbound to S.R. 704/Okeechobee Boulevard westbound; I-95 southbound to S.R. 706/Indiantown Road eastbound

Start Date: January 20, 2026

Completion Date: Summer 2026

Contractor: Ranger Construction Industries

Estimated Construction Cost: $1.2 Million

Point of Contact:

Kevin Wells — Community Outreach Specialist

Phone: 728-235-7218, Email: kevin@holtcommunications.net

Scope of Work

Project Improvements:

  • Installing a high friction surface on all ramps to enhance infrastructure resilience and improve vehicle safety.
  • Upgrading to new LED lighting and replacing the existing guardrail for the northbound S.R. 9/I-95 on-ramp from eastbound S.R. 704/Okeechobee Boulevard to enhance vehicle safety.
  • Installing a digital speed feedback sign on the northbound S.R. 9/I-95 off-ramp to westbound S.R. 786/PGA Boulevard.
  • Upgrading signage and pavement markings to enhance visibility and safety.