State Road (S.R.) 9/I-95 Resurfacing, Restoration, and Rehabilitation (RRR) Project

Road Number: S.R. 9

Local Road Name: I-95

County: Martin

Contract Number: T4722

Project Number: 449159-1-52-01, 449160-1-52-01

Project Length: 17.002 miles

Project Limits: S.R. 9/I-95 from north of County Road (C.R.) 708/SE Bridge Road to the Martin/St. Lucie County line

Start Date: June 22, 2025

Completion Date: Fall 2028

Contractor: C.W. Roberts Contracting, Inc.

Estimated Construction Cost: $40,800,000

Point of Contact:

Kim Johnson — Community Outreach Specialist

Kim@holtcommunications.net or (772) 801-8736

Mark Freeman — FDOT Project Manager

mark.freeman@dot.state.fl.us or (772) 429-4904

Wendy McLellan Project Administrator 

wmclellan@allyeng.com or (561) 373-0787

 

Scope of Work and Project Improvements

  • Milling and resurfacing the S.R. 9/I-95 mainline from north of C.R. 708/SE Bridge Road to the Martin/St. Lucie County line to enhance safety and long-term resiliency.
  • Widening the northbound S.R. 9/I-95 entrance ramp shoulder from S.R. 76/SW Kanner Highway to improve safety and traffic operations.
  • Constructing new lighting to increase nighttime visibility; installing Wrong Way Vehicle Detection Systems (WWVDS) on S.R. 76/SW Kanner Highway, S.R. 714/SW Martin Highway, and C.R. 713/SW High Meadow Avenue ramps to improve safety.
  • Upgrading signage and pavement markings to enhance safety, functionality, and traffic operations.

Traffic Impacts

  • Single and double lane closures and interchange ramp closures on S.R. 9/I-95 are permitted nightly, Sunday through Thursday.
  • Nighttime closures will take place during the weekdays from 8 p.m. to 6 a.m.
  • Single and double lane closures on northbound and southbound S.R. 9/I-95 are permitted from 8:00 p.m. to 6:00 a.m. from north of C.R. 708/SE Bridge Road to south of S.R. 76/SW Kanner Highway.
  • Single and double lane closures on northbound SR 9/I-95, are permitted from 9:00 p.m. to 7:00 a.m. from south of S.R. 76/SW Kanner Highway to the Martin/St. Lucie County Line.
  • Single and double lane closures on southbound S.R. 9/I-95, are permitted from 7:30 p.m. to 5:30 a.m.
  • S.R. 9/I-95 ramp impacts will have single lane, and full ramp closures are permitted throughout the project limits, from 8:00 p.m. to 6:00 a.m.
  • Consecutive ramp closures will not take place at the same time.