Financial Number: 446103-1-52-01
Project Length: 0.569 Miles
Project Limits: SR-809/Military Trail from South of Dyer Boulevard to North of Flag Drive
Construction Start Date: Summer 2023
Construction End Date: Fall 2024
Estimated Construction Cost: $1.8M
Scope of Work:
- Repave the existing roadway
- Reconstruct sidewalk
- Upgrade curb ramps to meet Americans with Disabilities Act (ADA) standards
- Upgrade pedestrian signals, intersection lighting, pavement markings and signing to current standards
Construction Impacts:
- Lane closures during off-peak hours will be required
- Milling and resurfacing operations will be sequenced to reduce the effects of construction on the community
- Access to adjacent properties will be maintained at all times
Contact Information:
Scope of Work:
446103-1-52-01 SR 809 RRR Fact Sheet
|