SR 800/Spanish River Boulevard Over the Intracoastal Waterway (ICWW) Scour Countermeasures Project

Financial Number: 441466-1-52-01

Project Length: 0.092 miles

Project Limits: SR 800/Spanish River Boulevard Bridge #930266 & #930154

Start Date: January 9, 2024

Completion Date: Early 2025

Contractor: Oceanik US, Inc.

Estimated Construction Cost: $2.1 million

Virtual Public Meeting:

Scope of Work:

Installing Articulated Concrete Block (ACB) at the river bed to protect the bridge foundations from erosion on the eastbound and westbound SR 800/Spanish River Boulevard bridges.

Point of Contact:

Document:

PDF IconProject Info Flyer

Click here for upcoming lane closures

 

Project Photos

Pre-Construction

Click to view enlarged version/details

During Construction

Click to view enlarged version/details
SR800_underwatersurvey_0224 SR800scour_acbmats_0224 (2) SR 800_Spanish River Blvd_ACB Mat placement activities_July2024 SR 800_Spanish River Blvd_ACB Mat placement activities_ July 2024
Placement of Articulated Concrete Block Mat on east side_Sept042024Placement Articulated Concrete Block Mats_east side_ Aug282024Cutting_Removal of abandoned submarine cable_ Oct24SR 800_Spanish River Blvd_Placement of ACB mat on west side_Nov24
SR 800_Spanish River Blvd_ ACBM placed on west side_Nov24



Please click on a link below to view construction projects
in other areas of Palm Beach County:
  I-95 Palm Beach CountyI-95 Construction Palm Beach County Northern Palm Beach CountyNorthern Palm Beach County
  Southern Palm Beach CountySouthern Palm Beach County Western Palm Beach CountyWestern Palm Beach County
  Central Palm Beach CountyCentral Palm Beach County Bridges Palm Beach CountyBridge Construction Palm Beach County
Florida Department of Transportation
Florida Department of Transportation
FDOT District Four Youtube
Kids Zone
zero