Financial Number: 442891-1-52-01
Project Length: 0.175 miles
Project Limits: Along SR 5/US 1 over Earman River (C-17) Bridge from Northlake Boulevard to
Anchorage Drive South in Palm Beach County
Virtual and In-Person Public Meeting: Thursday, March 24, 2022, (from 6:00pm until 7:30pm)
Projected Letting: December 2022
Construction Start Date: Spring 2023
Completion Date: Summer 2024
Estimated Construction Cost: $7.5 M
Scope of Work:
- Bridge replacement
- Roadway reconstruction and widening
- Milling and resurfacing
- Landscape features on the bridge
- Roadway lighting
- Signalization to install pedestrian signals on the north leg of SR 5/Northlake Boulevard
- Signing and pavement markings
- Replacement of deficient pedestrian curb ramps to comply with Americans with Disabilities Act (ADA) standards.
Construction Impacts:
- All work will be done in phases to reduce the impact of construction to the community
- All lane closures will occur during non-peak hours
- No full roadway closures will occur
- Access to businesses and residents will be maintained at all times during construction