Financial Number: 446174-1-52-01
Project Length: 0.903 miles
Project Limits: SR 786/ PGA Boulevard from East of SR 9/I-95 to East of Fairchild Gardens Avenue
Virtual Public Workshop: Wednesday, November 16, 2022 at 5:00 p.m.
In-person meeting: The in-person public meeting is scheduled to occur on Thursday, November 17, 2022 at 5:00 p.m. at Marriott Palm Beach Gardens.
Production Date: 06/5/23
Projected Letting Date: October 25, 2023
Start Date: Spring 2024
Completion Date: Spring 2025
Estimated Construction Cost: $3.25 Million
Scope of Work:
- Repave existing travel lanes.
- Update pedestrian curb ramps, including new yellow detectable warning pads, to meet current Americans with Disabilities Act (ADA) standards.
- Improve signing and pavement markings.
- Upgrade lighting and pedestrian signals at Lake Victoria Gardens Avenue and Fairchild Gardens Avenue intersections.
- Install advance warning flashers facing eastbound traffic in advance of the Lake Victoria Gardens Avenue signalized intersection.
- Upgrade traffic signal vehicular video detection and controller cabinets.
Construction Impacts:
- All work will be done in phases to reduce the impact of construction to the community.
- Daytime temporary lane closures during nonpeak hours will occur.
- There will be no complete road closures.
- Business access will be maintained at all times.
- Pedestrian detours will be provided for pedestrian curb ramp closures.
Project Benefits:
- Restore and extend the pavement service life.
- Enhance motorist and pedestrian safety.